Latest Updates
- 83.6% of lots sold (due to 9 lots on Loney Cres that are officially part of Phase 2)
- Request to complete ditches (grading, topsoil and sod) has been submitted to city
- Request to complete top layer of asphalt submitted to city
- 9 remaining lots on Loney Cres are now serviced & available for sale
Phase 2 Action List
Item | Action |
Complete |
Incomplete |
83.6% of lots sold (46/55 lots sold) | NA | ||
9 lots on Loney Cres be readied for sale | Complete 2017 | ✔ |
|
Speed Limit Signs (40km/h) | Pending |
× |
|
Complete ditches (grading, top soil, sod) | Requested |
× |
|
Complete top layer of asphalt | Complete 2016 |
✔ |
|
Stop Sign (Whiteside at Iveson) | Complete 2016 |
✔ |
|
Potholes (Iveson at Whiteside) | Complete 2017 |
✔ |
|
Cost estimate for completion | Requested |
× |
|
Clarify Subdivision Phase Boundaries (as city had incorrect info) | Corrected 2017 |
✔ |